Mother of the Nation Festival 2017

Project: Mother of the Nation Festival 2017

Client: Abu Dhabi Tourism & Cultural Authority / Flash Entertainment
Format: Public Event
Location: Corniche – Abu Dhabi
Date: 24.03 – 04.04.2017
Job: Site Manager / Health & Safety Manager

  • Event Safety Management Plan (EMSP)
  • Risk Assessments
  • Venue and Site Management
  • Fire Safety
  • Major Incident Emergency Planning
  • Emergency evacuation plan
  • Supervising suppliers
  • Communication concept (announcement system with overwrite function and radio network
  • Crowd management and design of entrance points
  • Permission process with local authorities
  • Inspection and check of all temporary structures in cooperation with structural engineer
  • Inspection and check of all electrical installations